Compton Hauling Station

12/1/2015

 

Description of Project:

Compton Hauling Station is a fully operational waste hauling station. Pride assisted the site with installation of Phase I stormwater upgrades. Phase I consisted of pothole investigation, install of a trench drain at the front entrance gate to prevent runoff, installation of stormwater basins, stormdrain piping, concrete drive approaches, construction of concrete outlet boxes with filters and catch basin inlet filter upgrades.
Picture
Picture

Scope of Work Performed:

  • Pothole investigation to confirm design criteria and verification of underground utilities
  • Excavation and grading of two (2) stormwater basins with install of aggregate protected slope and overflow concrete structure
  • Install of ACO S300K trench drain system at main entrance gate
  • 300-LF of below grade 10-inch PVC stormdrain piping with clean-out system
  • Abandonment of existing stormwater sampling ports
  • Install of Filtrexx Soxx at various location around the site
  • Repaved asphalt areas removed during construction

Before

Picture

After

Picture

Project Successes:

  • Maintained project schedule while working around onsite operations. Pride’s work was performed during normal work hours at three (3) of the active gates. Pride completed work while having minimal impact to operations.
  • Field crews were able to provide client with actual field elevations to redesign stormdrain piping
  • Project was completed ahead of schedule and on budget

Before

Picture

After

Picture

Additional Info:

Location: Compton, CA
Project Super: Adam Wenzel – (714) 465-8108
Project Manager: Todd St. Peter – (714) 240-4983
Actual Date of Completion
: December 2015
Request More Info

Comments are closed.
Picture

Home

About

Services

Projects

Contact

Copyright © 2019   |   714-240-4983   |   [email protected]​
  • Home
  • About
  • Services
  • Projects
  • Contact