GI Industry Hauling & Transfer Station

3/5/2018

 

Description of Project:

GI Industry Hauling & Transfer Station is a fully operational waste handling facility. Pride provided install of final stormwater upgrades for the facility. Stormwater upgrades included install of an underground stormwater infiltration and discharge system. The project required mass excavation and grading, install of perforated corrugated metal piping, concrete inlet structures, numerous concrete stormwater control structures and concrete/asphalt revitalization.
demolition excavation

Scope of Work Performed:

  • Demolition of existing asphalt, concrete and existing features
  • Install of sheet pile shoring within infiltration gallery excavation footprint
  • Excavation, load-out and hauling of approx. 4000-CYDS of existing earthwork materials
  • Placement of sand bedding material and install of 730-LF of 120-inch CMP piping
  • Procure, delivery and install of approx. 4500-tons of angular stone
  • Procure and install numerous 48-inch drain inlets, along with 18-inch and 10-inch PVC piping
  • Procure/set/install diverter and bypass structures, high velocity interceptor/horizontal flow clarifier, junction/confluence structure at two (2) different locations at site
  • Install approx. non-woven geotextile over angular stone within infiltration gallery
  • Install of three (3) concrete manholes access points with frames and covers
  • Procure/deliver/set/install 40K gallon precast stormwater storage tanks with PVC C900 piping
  • Placement and compaction of class II base and install of new asphalt and concrete over disturbed areas

Project Successes:

  • Due to project constraints with truck hauling/parking, Pride was required to work around operational activities, which confined us to a truncated footprint on a daily basis
  • Due to constraints of the site, Pride worked 7-day work weeks, 12-hour work days to expedite the work. Project was completed within a 1-month period
PVC
Picture

Additional Info:

Location: Simi Valley, CA
Project Super: Adam Wenzel – (714) 465-8108
Project Manager: Todd St. Peter – (714) 240-4983
Request More Info

Comments are closed.
Picture

Home

About

Services

Projects

Contact

Copyright © 2019   |   714-240-4983   |   [email protected]​
  • Home
  • About
  • Services
  • Projects
  • Contact